Global Petroleum Show 2012
ConXtech will be exhibiting at the Global Petroleum Show (GPS) in booth #3002.
Read More »C-BIP Toronto: Where do supply chains emerge?
ConXtech’s CEO Robert Simmons takes part in panel discussion 2: Assemblies + Systems
Read More »ConXtech’s Innovative Connections Used at Stanford Law School
Degenkolb Engineers Honored with American Council of Engineering Award
Team Delivered “Space Faster and Cheaper, Producing Vision for Intellectual Openness.”
On February 7, 2012, Degenkolb Engineers’ structural team was presented the American Council of Engineering Companies (ACEC) Engineering Excellence Honor Award for Stanford University’s new William H. Neukom Law Building. Completed in May, 2011, the building is a $40 million, 65,000 square-foot, 3-story academic and office facility. Degenkolb Engineers used ConXtech’s ConXL Chassis Based Modular® steel framing system for the project.
Read More »ConXtech Hosts AISC Steel Day 2011
Design and build your next project FASTER, BETTER, SAFER AND GREENER™
with CONX® CHASSIS BASED MODULAR™ building system.
Read More »
Pipe Rack
| ConXR Ongoing | |
|---|---|
| Location: | Bakersfield, CA |
| Owner: | Aera Energy LLC |
| GC: | Aera Energy LLC |
| Engineer: | Joshua Moody, S.E. |
| Architect: | Technical Services & Management |
ConXtech Erects Steel in 9 Days for CoreSite’s Santa Clara Data Center
ConXtech’s ConXL™ product delivered unprecedented construction efficiencies as well as the robust steel frame for the 101,000 SF, LEED Gold data center
ConXtech® Space Frame Systems, a leading provider of innovative, robust structural steel solutions, today announced the completion of ConXL steel framing in nine days at CoreSite Realty Corporation’s (NYSE: COR) 101,000 square-foot Santa Clara data center. ConXtech began erecting on January 27th and topped out steel on the project on February 9th. The ConXL product addressed CoreSite’s need for a robust, long-span steel data center frame delivered cost-effectively and with increased speed to market.
Read More »Navy Lodge
| ConXR Complete | |
|---|---|
| Location: | North Island, Coronado, CA |
| Total sf: | 152,000 |
| Owner: | US Navy (NAVFAC) |
| GC: | RQC – RQ Construction |
| Engineer: | GPLA – Gregory P. Luth and Associates |
| Architect: | RQC – RQ Construction |
CoreSite
| ConXL Complete | |
|---|---|
| Frame erected in 9 working days | |
| Location: | Santa Clara, CA |
| Total sf: | 101,000 |
| Owner: | CoreSite |
| GC: | Matt Construction |
| Engineer: | FBA Engineers |
| Architect: | DCM |