Modular Pipe Rack

Modular Pipe Rack
ConXR
Location: Bakersfield, CA
Owner: Aera Energy LLC
GC: Aera Energy LLC
Engineer: Joshua Moody, S.E.
Architect: Technical Services & Management
Days to Erect: 20

PROJECT NARRATIVE

Water Processing Plant on Central California Oil Field
ConXtech has an ideal solution for Pipe Rack and Processing structures. Safe and rapid to erect, ConXtech’s modular approach brings efficiencies in cost and materials. The brace free and structurally robust ConXR System made it possible to design for the worst case scenario, and then fabricate and erect the structure before the piping layout/design was finalized. Other modular pipe rack components designed and provided by ConXtech will be integrated into the structure as the project progresses.

 

PROJECT CHALLENGES / SPECIAL CONSIDERATIONS

The Owner’s Senior Project Manager estimates that utilizing the ConX System will save their company 1 year off of an otherwise 4 year schedule. Starting production in this oil field one year earlier makes the ROI measurable and significant.
Pipe Rack Brochure Download Project Sheet

 

PRESENTATION AT 2011 LCI CONFERENCE

Watch this video recording of a presentation from the 13th Annual Lean Construction Institute Congress 2011, in which an Aera project engineer explains (at 21:40 min mark) how using the prefabricated ConX System brought significant time and monetary savings to the owner.

 

WATCH VIDEO

Introduction to ConXtechModular Pipe Rack From Design to Construction

VIDEO: See how the detailing, fabrication, and erection of a Water Treatment Plant was greatly simplified using the ConX Modular Pipe Rack solution.

 