Boldt Construction Testimonial

February 5, 2026

From zero to three stories in just eight days!

The Sutter Health Folsom Care Complex team set 825 pieces of structural steel in eight days, completing the structural phase 50% faster than traditional methods.

This success was powered by meticulous pre-planning, the innovative ConXtech system and an Integrated Lean Form of Agreement with all partners, including Boulder Associates, Mazzetti, M3 MEP, M3 Components, Criterion – Medical Equipment Planning, Drawings, Procurement & Logistics, Buehler and Teichert together in a collaborative big room environment.

When Lean principles meet teamwork and technology, incredible things happen. Congratulations to everyone involved for redefining what efficiency in healthcare construction looks like!

“The alignment and partnership up front with any trade partner is crucial to the success of any project team. Without this collaboration, I can confidently say that we wouldn’t have experienced the full speed and efficiency of ConXtech’s system and crews.” Brian Melcher

“This is what happens when Lean thinking, real collaboration, and smart technology come together. Huge respect to the entire team for raising the bar in healthcare construction.”